We have started the construction of a roundabout in Český Krumlov, at the intersection of roads II/157 and II/160.
The construction of the intersection itself was preceded by the construction of a 112 m long sewer, including shafts and sewer connections. At the same time, due to the water supply, a 11.5 m long steel protective pipe with a diameter of 500 mm had to be placed under the road, into which the water supply line was relocated.
The construction is complicated mainly by the limited working space and almost no space for material storage. All excavated materials are therefore immediately transported to a recycling dump.
The construction is being carried out by our colleagues from the Transport Construction JIH division, in the Český Krumlov area, and it should be completed within 6 months.