We completed the reconstruction of the road a full 11 months ahead of schedule!
In the consortium, we handed over the reconstructed road II/130 in the section D1 – Ledeč nad Sázavou for early use. The original deadline was set for October 2025!
On this 8.5 km long route, we utilized cold recycling technology of the sub-base layers to improve the substrate quality. We then laid new asphalt layers and renewed the culverts and safety equipment, thereby increasing safety and comfort for all motorists.
This year, only the structures off the roadway remain to be completed.