Construction began in the fall of 2025, and our phase of the project kicked off at the end of March of this year. In early June, we successfully brought the roundabout we built into full operation; until then, traffic had been routed in alternating directions through it.
Following the completion of this phase, work will shift to the main route of the bypass, where we will continue construction of the main section of Road I/14 after the summer break. In addition to the main route, the project also includes a pair of roundabouts, bridge structures, realignments of lower-class roads, and modifications to utility networks. The total length of the bypass’s main route is 1,712 meters.
We are carrying out the entire project as a consortium, and its completion is scheduled for 2027.